The FBI lesson why Enterprise architecture is so important to the enterprise.
First of all I want to thank Alex Komissarov for sending
me this information.
The FBI has been running
a project called Trilogy for the
last 3.5 years. The project aim is to replace FBI IT
solution to increase FBI productivity. Trilogy reach major
milestone in April 2004 but with delays and cost increase.
To understand the reasons the FBI assign audit committee
to write down an audit report.
The audit report found various reasons account for the
delays and associated cost increases in the Trilogy
project, including:
-
poorly defined and slowly evolving design
requirements,
-
contracting weaknesses,
-
IT investment management weaknesses,
-
lack of an Enterprise Architecture,
-
lack of management continuity and oversight,
-
unrealistic scheduling of tasks,
-
lack of adequate project integration, and
-
inadequate resolution of issues raised in reports on
Trilogy.
Pay attention that one of the leading reasons is
a lack of enterprise
architecture!
Here some more detailed information from the report
regarding the
You can view the entire report at :
http://www.usdoj.gov/oig/audit/FBI/0507/final.pdf